CEBU CITY, Philippines — Due to extensive damage in wirings and infrastructure in interior communities, power in Metro Cebu may not be fully restored by January 31.
Engineer Raul Lucero, president and chief operating officer (COO) of Visayan Electric, said more work would need to be done in the inner portions of their franchise area.
Lucero told reporters in an interview on Thursday, January 27, that they are most likely to restore 90 percent of their franchise area by the end of this month.
The Visayan Electric executive said they underestimated the damage Typhoon Odette (international name: Rai) left in a city or town’s innermost portions, particularly residential areas.
“Pero dinha nga nakasulod nami sa mga sudlonon nga mga lugar, dinha namo nakita nga mas daghan gyud kaayo or mas grabe ang guba didto. Meaning, na underestimate namo ang damage,” said Lucero.
(Now that we have entered the innermost portions, there we saw the bigger and worse damage. Meaning, we underestimated the extent of the damage.)
“And maybe by next week, January 31, naa ra mi sa mga 90 percent so di gyud namo ma achieve ang 100 percent,” he added.
(And maybe by next week, January 31, we will only be at 90 percent so we really could not achieve the 100 percent yet.)
To recall, Visayan Electric earlier forecasted that they may be able to reach full restoration status of their franchise area by January 31.
As of January 27, their latest re-energization bulletin showed that electricity has returned in around 87.27 percent of its total consumers. This translates to 413,841 reenergized customers out of the total 474,182.
Lucero also said they were not expecting to reach a restoration status of 100 percent, saying some of their customers had to redo their properties’ electrical wirings from scratch.
“Sure mi dili mi kaabot ug 100 percent. Ngano man? Kay naay mga customers nga nananguba ang balay. Ig adto namo dadto, wa pa nahuman ug ayo ang balay. So di gyud maigo ug 100 percent. Basin mga 99 percent. Just less than 100 percent,” he continued.
(I am sure that we cannot achieve 100 percent. Why? Because there are customers, whose houses were destroyed. When we go there, repairs for their houses are not yet done. So we cannot hit the 100 percent. Perhaps, 99 percent. Just less than 100 percent.)
In the meantime, Lucero assured their consumers that their restoration works would continue.
“Naningkamot gyud mi nga padayunon ang pag energize atong customers. Akong giassure gipangitaan namo ug paagi tanan nato customers ma reenergize. Dili mi muundang hangtud dili ma energize ug balik ang tanan nga customers nga naa nay mga balay,” he added.
(We will work hard that we will continue to reenergize our customers homes. I assure them that we will find a way to have all our customers’ houses reenergized. We will not stop until we can reenergize all our customers’ houses.)
Visayan Electric covers Liloan, Consolacion, Minglanilla, San Fernando and the cities of Cebu, Mandaue, Talisay, and Naga.
RELATED STORIES
Visayan Electric restores power to over 80% of customers within franchise area
Fully restored power by end of January 2022 — Visayan Electric