Metal bracing for overhead wires — Veco

By: Jose Santino S. Bunachita March 04,2016 - 10:13 PM

MAY 1 DEADLINE FOR SAGGING WIRES/MARCH 4, 2016: Sagging and danggling utility wires were long been seen at F. Ramos and Arlington Fund street which is an eyesore to the public. The Visayan Electric Company (VECO) will be putting up 25 steel brackets to the City's Central Business district to especially prevent telcos sagging wires. They are now coordinating with the telcos for its implementation to clear City for sagging wires.(CDN PHOTO/JUNJIE MENDOZA)

The Visayan Electric Co. plans to install steel braces to carry overheads wires in Cebu City’s central business district such as this area along F. Ramos St. and Arlington Pond St. (CDN PHOTO/JUNJIE MENDOZA)

THE Visayan Electric Company (Veco) will be installing metal bracing or brackets to carry bundles of overhead wires in selected areas in the Cebu business district.

The steel bracing  will require less poles on the streets to support the overhead wires, said Adrian Fabian, Veco streetlight and pole utilities department head yesterday.

“What Veco is doing now is we’re fabricating brackets or crossarms where they can hang the wires. Our first area is within the business district. We’ve identified 25 areas where we’ll put these soon,” Fabian said yesterday.

While they’re preparing these, he said other telecommunications and utilities companies are still busy bundling the dangling wires all over the city – a promise they gave to Cebu City Mayor Michael Rama after a series of accidents involving dangling wires.

If their brackets can hold the wires, this will mean that the telcos might just be able to fulfill the mayor’s “one-pole” policy for utilities, Fabian said.

Fabian was referring to the telcos and utility companies’ promise to remove all dangling wires in the city by May 1, which was an extension of the October deadline set by Mayor Micheal Rama.

Right now, he said they’re still testing the brackets’ capacity to carry the bundles of wires.

Veco has also formed a crew to survey poles within the business district to check if these are rotten or leaning.

Fabian said they will then notify the concerned company about the issue. If they don’t respond within seven days, Veco will  remove them.

Fabian said they’re optimistic that they can meet the target if they just focus on the business district./Reporter Jose Santino S. Bunachita

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

Read Next

Disclaimer: The comments uploaded on this site do not necessarily represent or reflect the views of management and owner of Cebudailynews. We reserve the right to exclude comments that we deem to be inconsistent with our editorial standards.

TAGS: Cebu City Mayor Michael Rama, Visayan Electric Company

We use cookies to ensure you get the best experience on our website. By continuing, you are agreeing to our use of cookies. To find out more, please click this link.