BAC to resolve WTCI blacklisting before year-end

Rosalie Abatayo 11/18/2019

CEBU CITY, Philippines —  The Capitol’s Bids and Awards Committee (BAC) is eyeing to resolve the blacklisting of WT Construction Inc. (WTCI) before 2019 ends. WTCI is the contractor of the scrapped P1.3-billion Provincial Resource Center Building…

Davide: WT may sue province for stopping resource center project

Rosalie O. Abatayo 07/17/2019

CEBU CITY, Philippines — WT Construction Inc. (WTCI) the contractor of the proposed P1.3-billion Capitol Resource Center, is not obliged to backfill the now excavated site of the cancelled project. Instead, the firm may file a case…

Gwen to WTCI: Restore excavated Capitol lot in 48 hours or be blacklisted

Rosalie O. Abatayo 07/16/2019

CEBU CITY, Philippines—The “abolished” Capitol Resource Center project may be the last transaction that WT Construction Inc. (WTCI) will have with the Cebu provincial government. This as Governor Gwendolyn Garcia threatens to blacklist WTCI from undertaking future…

Capitol to hold WT equipment until Capitol grounds are restored

Rosalie Abatayo 07/08/2019

CEBU CITY, Philippines —At least P6.9 million shall be needed in order to restore to level ground the excavated part of the Provincial Capitol Compound where the 20-story Capitol resource center was supposed to stand. But Governor…

Garcia denies WT Construction’s request to pull out equipment from resource center project site

Rosalie O. Abatayo 07/03/2019

CEBU CITY, Philippines —After it was ordered to stop building the 20-story resource center, WT Construction Inc. asked the provincial government that it will be pulling out its survey instrument from the project site. WTCI, the contractor…

Garcia orders permanent halt of resource center construction

Rosalie O. Abatayo 07/01/2019

CEBU CITY, Philippines — Is it now the end of the 20-story Cebu Provincial Resource Center project? Governor Gwendolyn Garcia, in her first executive order on Monday, July 1, has ordered for the “immediate stoppage and permanent…

Bizman files Ombudsman case vs Davide, Capitol execs over a bidder’s qualification to build P1.3B resource center project

Rosalie O. Abatayo 01/28/2019

  CEBU CITY, Philippines — A Cebuano businessman today went to the Visayas Ombudsman  to lodge a complaint against Cebu Governor Hilario Davide III and at least five other Capitol officials for prequalifying WT Construction to bid for…

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies. Learn more here.