cdn mobile

COA flags delay in P1.5B hospital facility upgrades

By: Inquirer.net July 11,2017 - 11:00 PM

MANILA — The Commission on Audit (COA) has called out the Department of Health (DOH) for various delays in the implementation of P1.505 billion worth of infrastructure projects under the Health Facilities Enhancement Program (HFEP).

The HFEP provides funding assistance for infrastructure and equipment of government health facilities nationwide, with the aim of improving the delivery of basic, essential and specialized services. A total of P83.365 billion was invested from 2010 to 2016 to upgrade, rehabilitate and construct health facilities.

But COA said P1.188 billion worth of infrastructure projects were not completed within the contract timeframe, while P291.748 million worth of completed infra projects were found to be unutilized.

Concerned DOH agencies include Regions V (Bicol), VI (Western Visayas), and XI (Davao Region) offices, as well as the Quirino Memorial Medical Center (QMMC) in Quezon City, Bataan General Hospital (BGH), and Cotabato Regional and Medical Center (CRMC).

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

Read Next

Disclaimer: The comments uploaded on this site do not necessarily represent or reflect the views of management and owner of Cebudailynews. We reserve the right to exclude comments that we deem to be inconsistent with our editorial standards.

TAGS: COA, delay, facility, flags, hospital
Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies. Learn more here.